Experience
Project Info:
Owner:
Washington Mills - SMG Management
Technologies/Materials:
Primed and painted steel beams and plates
Architect:
TEC, Inc.
Project Value:
$451,275
Project Highlights:
The project repaired, renovated, and painted the Mill Street bridge in Lawrence, MA.
Owner:
Washington Mills - SMG Management
Technologies/Materials:
Primed and painted steel beams and plates
Architect:
TEC, Inc.
Project Value:
$451,275
Project Highlights:
The project repaired, renovated, and painted the Mill Street bridge in Lawrence, MA.
Lawrence Bridge Repair & Painting - Lawrence, MA
The project invloved the fabrication, installation and painting of bridge components:
- 2 primed steel channels in the NE corner of the bridge.
- 7 steel beams at the south abutment of the bridge
- Steel plate replacements over floor beams in four locations of the bridge
- 6 PVC down spouts under the bridge drains
Additionally, a six foot section of the bridge railing was straighted. welded, and repaired.