Experience
Project Info:
Owner:
Algonquin Power
Technologies/Materials:
Sluice Gate, Obermeyer Inflatable Flash Board
Engineer:
Kleinschmidt
Project Value:
$350,000
Project Highlights:
A 150 foot concrete wall was built to protect existing dam structures
Owner:
Algonquin Power
Technologies/Materials:
Sluice Gate, Obermeyer Inflatable Flash Board
Engineer:
Kleinschmidt
Project Value:
$350,000
Project Highlights:
A 150 foot concrete wall was built to protect existing dam structures
Franklin Sluice Gate and Flash Board Installation - Franklin, NH
The Industrial Services Group provided the pre-construction and installation work for three projects at the Steven’s Mill/River Bend Facility in Franklin, NH. A six foot by eleven foot electrically operated sluice gate was created by the team, and was Installed at the site along with an Obermeyer Hydro inflatable flash board system. Additionally, a 150 foot concrete flood wall was built to protect the existing structures.